|
|
|
|
Cleaned out Main Catch Basin |
|
Approximately 3 feet of sediment at the bottom
restricting drainage into soil |
|
Catch basin can only absorb a fraction of design
due to roots and silt |
|
Conducted soil permeability test – Schofield
engineer |
|
Dug two test holes |
|
Measured ability of soil to absorb water (16
inches of water per hour) |
|
Looked for level of water table (none found down
to -13 ft.) |
|
Good news |
|
Determined the volume of water that must be
absorbed in a given time (2 yr, 10 yr, 25 yr and 100 yr storms per standard
Framingham models) |
|
Assessed the current design – less than 1/6 of
what is required |
|
Designed an upgrade to accommodate water from a
100 yr storm and be sustainable (with maintenance) for 50 years |